BREAKDOWN OF UNIT PRICE
Item:0213. Earth Filling with earth availabl
Basis:1000cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
6.000
No.
550.00
3300.00
Skilled Labour
2.000
No.
600.00
1200.00
Sub-Total(L1)
4500.00
158.92
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
No.
550.00
275.00
Sub-Total(M2)
275.00
9.71
Total(1)
168.63
Add over head on Total(1)
3.5 %
5.90
Add Profit on Total(1)
10.0 %
16.86
Total(2)
22.76
Add VAT on Unit Price
5.5 %
1.32
Unit Price
24.09
Say
24
per cum