BREAKDOWN OF UNIT PRICE
Item:021004. Sand Filling-F.M.=2.2
Basis:100cft
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.2.2)
130.000
cft
53.80
6994.00
Sub-Total(A4)
6994.00
2469.93
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.667
No.
550.00
366.85
Head Mason
0.125
No.
800.00
100.00
Sub-Total(L1)
466.85
164.87
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.100
No.
550.00
55.00
Sub-Total(M2)
55.00
19.42
Total(1)
2654.22
Add over head on Total(1)
3.5 %
92.90
Add Profit on Total(1)
10.0 %
265.42
Total(2)
358.32
Add VAT on Unit Price
5.5 %
20.85
Unit Price
379.17
Say
379
per cum