BREAKDOWN OF UNIT PRICE
Item:021001. Sand Filling-F.M.=0.5
Basis:100cft
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.5)
130.000
cft
15.30
1989.00
Sub-Total(A4)
1989.00
702.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.667
No.
550.00
366.85
Head Mason
0.125
No.
800.00
100.00
Sub-Total(L1)
466.85
164.87
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.100
No.
550.00
55.00
Sub-Total(M2)
55.00
19.42
Total(1)
886.71
Add over head on Total(1)
3.5 %
31.03
Add Profit on Total(1)
10.0 %
88.67
Total(2)
119.71
Add VAT on Unit Price
5.5 %
6.97
Unit Price
126.67
Say
127
per cum