Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:0209. Remove Sludge, Sand-FM.8=1:10
Basis:1000cft
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
100.000
cft
16.70
1670.00
Sub-Total(A4)
1670.00
58.98
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hire charge-Truck
5.000
trip
2300.00
11500.00
Sub-Total(E1)
11500.00
406.12
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
19.000
No.
550.00
10450.00
Sub-Total(L1)
10450.00
369.04
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
4.000
No.
550.00
2200.00
Sub-Total(M2)
2200.00
77.69
Total(1)
911.83
Add over head on Total(1)
3.5 %
31.91
Add Profit on Total(1)
10.0 %
91.18
Total(2)
123.10
Add VAT on Unit Price
5.5 %
7.16
Unit Price
130.26
Say
130
per cum