BREAKDOWN OF UNIT PRICE
Item:0105. Monthly progress meeting at site-
Basis:1no.
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Progress meeting arrange
1.000
LS
1718.75
1718.75
Sub-Total(M1)
1718.75
1718.75
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.469
No.
550.00
257.95
Sub-Total(M2)
257.95
257.95
Total(1)
1976.70
Add over head on Total(1)
3.5 %
69.18
Add Profit on Total(1)
10.0 %
197.67
Total(2)
266.85
Add VAT on Unit Price
5.5 %
15.53
Unit Price
282.39
Say
282
per mon