ITEM RATE | |||
---|---|---|---|
Click on Code to see the Shedule Items or Go Home | |||
B3 | Labour-Substructur-2 | ||
Code | Item | Unit | Rate(Tk.) |
B301 | Excavation upto 16ft dept | cft | 15.00 |
B302 | Excavation from 16-33ft | cft | 20.00 |
B303 | Excavation from 33-50ft | cft | 25.00 |
B304 | Excavation from 31-36ft | cft | 16.00 |
B305 | Bracing Installing -Joist | kg | 25.00 |
B306 | Bracing Remove-Joist | kg | 18.00 |
B307 | MS Pipe Driving | No. | 8000.00 |
B308 | Structure-Mat-Basement-3 | sft | 200.00 |
B309 | Structure-Basement-2 | sft | 195.00 |
B310 | Structure-Basement-1 | sft | 190.00 |
B311 | Structure-Ground-Level | sft | 185.00 |
B312 | Brick Work-125mm Thick | sft | 15.00 |
B313 | Brick Work-250mm Thick | cft | 18.00 |
B314 | Plaster-12mm Thick | sft | 10.00 |
B315 | Excavation above 0.0 ft | cft | 3.50 |
B316 | MS Rod Unloading1 | kg | 0.00 |
B317 | MS Joist Unloading | kg | 0.00 |
B318 | MS Plate Unloading | kg | 0.00 |
B319 | MS Pipe Unloading | kg | 0.00 |
B320 | Excavation upto 18m | cft | 14.55 |
B321 | Ready Mix Concer-Wall | cft | 35.00 |
B322 | Ready Mix Concret-Col/Bea | cft | 50.00 |
B323 | Ready Mix Concrete-Base2 | cft | 77.50 |
B324 | Ready Mix Concrete-Base-1 | cft | 100.00 |
B325 | Shuttering-Sub-structure | sft | 45.00 |
B326 | Readymix Concreting-Mat | cft | 45.00 |
B327 | Re-bar Fabrication-Substr | kg | 12.00 |
B328 | Cashion Shuter-Place/rem | sft | 77.50 |
B329 | Sand Lift, remove fm Casi | cft | 70.65 |
B330 | Salvage-Joist/ Pipe Cut | ton | 10000.00 |
B331 | KIngPost Pile Breaking | cft | 250.00 |
B332 | Salvage-Joist/ Pipe Lift | ton | 10000.00 |
B333 | Salvage-Broken RCC Remove | cft | 100.00 |
B334 | MS Joist Fabricating | kg | 22.00 |
B335 | Bracing Dismantling-Joist | kg | 20.00 |
B336 | Bituminous Paper fixing | sft | 10.20 |
B337 | Readymix Concret-Substr | cft | 35.00 |
B338 | Readymix Conc-Basemn-Slab | cft | 38.50 |
B339 | Re-bar Unloading | kg | 3.00 |
B340 | Lifting-Excavator,Gen,Wel | no. | 99999.99 |
B341 | Lifting-Pipe,BillBoard,Si | no. | 99999.99 |
B342 | RCC Dismntl,remov fm cass | no | 99999.99 |
B343 | Steeicut,remov fm cassion | no. | 99999.99 |
B344 | Equip,tool lift,remove | no. | 99999.99 |
B345 | Cassion withdraw fm bot | sqm | 2322.55 |
B346 | Backfill Cashion void man | cft | 56.63 |
B347 | Air flow, exhaust fan-Cas | day | 5000.00 |
B348 | ShoreTemporary casing Drv | rft | 2714.11 |
B349 | Shore-Pile-Excavat-Fill | cft | 50.00 |
B350 | Shore Pile-Salvage rempva | no. | 99999.99 |
B351 | Shore Pile-Dewatering | day | 4480.00 |
B352 | Shore Pile-Air supply | day | 3500.00 |
B353 | Dewatering per cassion | day | 8000.00 |
B354 | Tie beam-Earth removal | cft | 50.00 |
B355 | Pile Head Finishing Manua | no, | 3000.00 |
B356 | Pile Rod clean, straigten | no. | 3000.00 |
B357 | Working Bed Preparation | sft | 139.35 |
B358 | Safety Railing i/c Paint | rft | 50.00 |
B359 | Fabrication Steel Shutter | sft | 75.00 |
B360 | Water Stopper fixing | rft | 20.00 |