BREAKDOWN OF UNIT PRICE
Item: (P01) PnG Fitout-Level-8
Basis:1 no.
F1.Fit-out
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PnG Fit out-Civil Works
1.000
LS
84808.00
84808.00
PnG Fit out-Fabrication
1.000
LS
97402.00
97402.00
PnG Fit out-Partition
1.000
LS
99999.99
99999.99
PnG Fit out-Furniture
1.000
LS
99999.99
99999.99
PnG Fit out-Doors
1.000
LS
99999.99
99999.99
PnG Fit out-Floor Fiish
1.000
LS
99999.99
99999.99
PnG Fit out-Ceiling Works
1.000
LS
99999.99
99999.99
PnG Fit out-Paint works
1.000
LS
99999.99
99999.99
PnG Fit out-Blinds n Scre
1.000
LS
39465.00
39465.00
PnG Fit out-Plumbing Work
1.000
LS
31530.00
31530.00
PnG Fit out-Electrical
1.000
LS
99999.99
99999.99
PnG Fit out-Networking
1.000
LS
99999.99
99999.99
PnG Fit out-Access Contro
1.000
LS
50548.00
50548.00
PnG Fit out-Signage
1.000
LS
34427.00
34427.00
Sub-Total(F1)
1138179.92
1138179.92
Total(1)
1138179.92
Add over head on Total(1)
5.0 %
56909.00
Total(2)
1195088.92
Add Profit on Total(2)
10.0 %
119508.89
Total(3)
1314597.81
Add VAT on Unit Price
5.5 %
80785.34
Add Income Tax on Unit Price
5.0 %
73441.22
Unit Price
1468824.37
Say
1468824
per LS