BREAKDOWN OF UNIT PRICE
Item: (N11B) Brick on End Edging-M/c made Bric
Basis:100 rft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Viti Sand (FM=0.5-0.8)
2.000
cft
15.00
30.00
Brick-M/c made
250.000
no.
9.50
2375.00
Sub-Total(A1)
2405.00
78.91
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour/ Helper
0.750
no.
550.00
412.50
Mason1
0.200
no.
700.00
140.00
Sub-Total(B2)
552.50
18.13
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
0.150
no.
700.00
105.00
Sub-Total(D1)
105.00
3.45
Total(1)
100.48
Add over head on Total(1)
5.0 %
5.02
Total(2)
105.50
Add Profit on Total(2)
10.0 %
10.55
Total(3)
116.06
Add VAT on Unit Price
5.5 %
7.13
Add Income Tax on Unit Price
5.0 %
6.48
Unit Price
129.67
Say
130
per Rm