Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (N10H2) Curb Stone-150x150x1000
Basis:3 rft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
0.080
bag
375.00
30.00
Local Sand (FM=1.2)
0.200
cft
18.00
3.60
Brick
4.800
no.
12.00
57.60
Sub-Total(A1)
91.20
91.20
A6.Landscape/ Road
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Curvbe-stone-150x150x1000
1.000
no.
250.00
250.00
Sub-Total(A6)
250.00
250.00
B7.Labour-Lanscaping
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Curbe-stone-150x150x1000
1.000
no.
50.00
50.00
Sub-Total(B7)
50.00
50.00
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer Machine
0.400
cft
5.00
2.00
Sub-Total(E1)
2.00
2.00
Total(1)
393.20
Add over head on Total(1)
5.0 %
19.66
Total(2)
412.86
Add Profit on Total(2)
10.0 %
41.29
Total(3)
454.15
Add VAT on Unit Price
5.5 %
27.91
Add Income Tax on Unit Price
5.0 %
25.37
Unit Price
507.43
Say
507
per Rm