Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (N10G) Sand Filling (FM=2.0)
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sylhet Sand (FM=2.2)
120.000
cft
54.00
6480.00
Sub-Total(A1)
6480.00
2288.41
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Filling
100.000
cft
15.00
1500.00
Sub-Total(B2)
1500.00
529.73
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Compactor
100.000
cft
5.00
500.00
Sub-Total(E1)
500.00
176.58
Total(1)
2994.71
Add over head on Total(1)
5.0 %
149.74
Total(2)
3144.45
Add Profit on Total(2)
10.0 %
314.44
Total(3)
3458.89
Add VAT on Unit Price
5.5 %
212.56
Add Income Tax on Unit Price
5.0 %
193.23
Unit Price
3864.68
Say
3865
per Cum