BREAKDOWN OF UNIT PRICE
Item: (N10F) Interlocking Block
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Viti Sand (FM=0.5-0.8)
30.000
cft
15.00
450.00
Sub-Total(A1)
450.00
48.44
A6.Landscape/ Road
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grey Uni-Block-222x110x80
388.000
no.
30.00
11640.00
Sub-Total(A6)
11640.00
1252.93
B7.Labour-Lanscaping
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Uni-paver laying
100.000
sft
30.00
3000.00
Sub-Total(B7)
3000.00
322.92
Total(1)
1624.29
Add over head on Total(1)
5.0 %
81.21
Total(2)
1705.50
Add Profit on Total(2)
10.0 %
170.55
Total(3)
1876.05
Add VAT on Unit Price
5.5 %
115.29
Add Income Tax on Unit Price
5.0 %
104.81
Unit Price
2096.15
Say
2096
per Sqm