BREAKDOWN OF UNIT PRICE
Item: (M02A) Prefabricated Frame Structure
Basis:1000 kg.
A5.Steel Structure
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Prefafricated Steel Struc
1000.000
kg
78.10
78100.00
Sub-Total(A5)
78100.00
78100.00
B6.Still Works-Erection
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Joist/ Angle Fabrication
1000.000
kg
20.00
20000.00
Joist/Angle/Deck Erection
1000.000
kg
6.00
6000.00
Sub-Total(B6)
26000.00
26000.00
D5.Other-Steel Struct
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Structure-Painting
1000.000
kg
3.50
3500.00
Steel Structure-Carrying
1000.000
kg
1.50
1500.00
Sub-Total(D5)
5000.00
5000.00
Total(1)
109100.00
Add over head on Total(1)
5.0 %
5455.00
Total(2)
114555.00
Add Profit on Total(2)
10.0 %
11455.50
Total(3)
126010.50
Add VAT on Unit Price
5.5 %
7743.66
Add Income Tax on Unit Price
5.0 %
7039.69
Unit Price
140793.85
Say
140794
per Ton