BREAKDOWN OF UNIT PRICE
Item: (E12A1) Door Frame-Chittagong Teak
Basis:2 cft
B5.Labour Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Door Frame Fixing
1.000
no.
500.00
500.00
Sub-Total(B5)
500.00
11771.67
Total(1)
11771.67
Add over head on Total(1)
5.0 %
588.58
Total(2)
12360.25
Add Profit on Total(2)
10.0 %
1236.03
Total(3)
13596.28
Add VAT on Unit Price
5.5 %
835.53
Add Income Tax on Unit Price
5.0 %
759.57
Unit Price
15191.37
Say
15191
per Cum