BREAKDOWN OF UNIT PRICE
Item: (E03B7) Plaster-RCC Surface-upto 4th Flor
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
1.200
bag
375.00
450.00
Local Sand (FM=1.2)
6.000
cft
18.00
108.00
Sub-Total(A1)
558.00
60.06
B5.Labour Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastering
100.000
sft
9.00
900.00
RCC Chipping
100.000
sft
8.00
800.00
Sub-Total(B5)
1700.00
182.99
Total(1)
243.05
Add over head on Total(1)
5.0 %
12.15
Total(2)
255.20
Add Profit on Total(2)
10.0 %
25.52
Total(3)
280.72
Add VAT on Unit Price
5.5 %
17.25
Add Income Tax on Unit Price
5.0 %
15.68
Unit Price
313.66
Say
314
per Sqm