Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (E02C4) 200mm Concrete Block-10th-11th
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
3.250
bag
375.00
1218.75
Local Sand (FM=1.2)
20.000
cft
18.00
360.00
ConcreteBlock-250x200x200
378.000
no.
30.00
11340.00
Sub-Total(A1)
12918.75
1390.57
B5.Labour Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Blockwork-200mm-10th-11th
100.000
sft
55.00
5500.00
Sub-Total(B5)
5500.00
592.02
D3.Shuttering-Hardware
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 40 times
1.000
set
15.00
15.00
Sub-Total(D3)
15.00
1.61
Total(1)
1984.21
Add over head on Total(1)
5.0 %
99.21
Total(2)
2083.42
Add Profit on Total(2)
10.0 %
208.34
Total(3)
2291.76
Add VAT on Unit Price
5.5 %
140.83
Add Income Tax on Unit Price
5.0 %
128.03
Unit Price
2560.63
Say
2561
per Sqm