BREAKDOWN OF UNIT PRICE
Item: (E02C1) 200mm Concrete Block-Basement
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
3.250
bag
375.00
1218.75
Local Sand (FM=1.2)
20.000
cft
18.00
360.00
ConcreteBlock-250x200x200
378.000
no.
30.00
11340.00
Sub-Total(A1)
12918.75
1390.57
B5.Labour Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Blockwork-200-Basement
100.000
sft
35.00
3500.00
Sub-Total(B5)
3500.00
376.74
D3.Shuttering-Hardware
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 40 times
1.000
set
15.00
15.00
Sub-Total(D3)
15.00
1.61
Total(1)
1768.93
Add over head on Total(1)
5.0 %
88.45
Total(2)
1857.38
Add Profit on Total(2)
10.0 %
185.74
Total(3)
2043.11
Add VAT on Unit Price
5.5 %
125.55
Add Income Tax on Unit Price
5.0 %
114.14
Unit Price
2282.81
Say
2283
per Sqm