BREAKDOWN OF UNIT PRICE
Item: (D09A8) CI Connection Pipe-300mm dia
Basis:18 rft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
0.120
bag
375.00
45.00
Local Sand (FM=1.2)
0.600
cft
18.00
10.80
Sub-Total(A1)
55.80
10.17
A3.Sanitary Materials
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Pipe-300mm dia
18.900
rft
750.00
14175.00
Sub-Total(A3)
14175.00
2583.79
B8.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
HCI Pipe -300mm fixing
18.000
rft
60.00
1080.00
Sub-Total(B8)
1080.00
196.86
D6.Others-Plumbing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hem
50.000
gm
1.00
50.00
Scaffolding-Plumbing
72.000
rft
1.00
72.00
U Clamp-300 mm
3.000
no.
250.00
750.00
Rowel Bolt-12mm
6.000
no.
35.00
210.00
Sub-Total(D6)
1082.00
197.22
Total(1)
2988.04
Add over head on Total(1)
5.0 %
149.40
Total(2)
3137.45
Add Profit on Total(2)
10.0 %
313.74
Total(3)
3451.19
Add VAT on Unit Price
5.5 %
212.08
Add Income Tax on Unit Price
5.0 %
192.80
Unit Price
3856.08
Say
3856
per Rm