BREAKDOWN OF UNIT PRICE
Item: (D08B3) CI Manhole Cove-600mm dia
Basis:1 no.
A3.Sanitary Materials
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI ManholeCover-600 Heavy
1.000
no.
2000.00
2000.00
Sub-Total(A3)
2000.00
2000.00
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover Fixing
1.000
no.
300.00
300.00
Sub-Total(B2)
300.00
300.00
Total(1)
2300.00
Add over head on Total(1)
5.0 %
115.00
Total(2)
2415.00
Add Profit on Total(2)
10.0 %
241.50
Total(3)
2656.50
Add VAT on Unit Price
5.5 %
163.25
Add Income Tax on Unit Price
5.0 %
148.41
Unit Price
2968.16
Say
2968
per each