BREAKDOWN OF UNIT PRICE
Item: (D08A) Inspection Chember-500x400
Basis:1 no.
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
1.253
bag
375.00
469.88
Local Sand (FM=1.2)
7.952
cft
18.00
143.14
Brick
179.000
no.
12.00
2148.00
Brick Chips-20mm
1.962
cft
110.00
215.82
Sub-Total(A1)
2976.83
2976.83
A5.Steel Structure
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Grating
15.000
kg
105.00
1575.00
Sub-Total(A5)
1575.00
1575.00
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Excavation
27.960
cft
8.50
237.66
Brick Flat Soling
9.175
sft
4.00
36.70
CC Work
2.180
cft
30.00
65.40
Brick Work
12.630
cft
8.00
101.04
Plaster with NCF
23.990
sft
6.00
143.94
Steel Grating-fixing
2.100
sft
50.00
105.00
Sub-Total(B2)
689.74
689.74
Total(1)
5241.57
Add over head on Total(1)
5.0 %
262.08
Total(2)
5503.65
Add Profit on Total(2)
10.0 %
550.36
Total(3)
6054.01
Add VAT on Unit Price
5.5 %
372.03
Add Income Tax on Unit Price
5.0 %
338.21
Unit Price
6764.26
Say
6764
per each