BREAKDOWN OF UNIT PRICE
Item: (C03C2) Steel Shutter-Slab-5th-9th Floor
Basis:350 sft
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shuttering-5th-9th Floor
350.000
sft
55.00
19250.00
Sub-Total(B4)
19250.00
592.02
D3.Shuttering-Hardware
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Shutter-use 3 time
350.000
sft
216.67
75834.50
MS Prop-use 20 times
88.000
no.
90.00
7920.00
Shutter Oil
350.000
sft
5.00
1750.00
Scaffolding-use 40 times
10.000
set
15.00
150.00
Nut-bolt, J-hook-use 8tim
12.000
kg
12.50
150.00
Hessain for Water Tight
350.000
sft
1.00
350.00
MS Box-50x100-use10 times
565.000
rft
13.50
7627.50
MS Pipe-50mm-use 20 times
162.000
rft
5.00
810.00
Sub-Total(D3)
94592.00
2909.11
Total(1)
3501.13
Add over head on Total(1)
5.0 %
175.06
Total(2)
3676.19
Add Profit on Total(2)
10.0 %
367.62
Total(3)
4043.80
Add VAT on Unit Price
5.5 %
248.50
Add Income Tax on Unit Price
5.0 %
225.91
Unit Price
4518.22
Say
4518
per Sqm