BREAKDOWN OF UNIT PRICE
Item: (C02D2) Re-bar Grage 60-3rd Floor
Basis:1000 kg.
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Deforme Bar Grade-400(60)
1050.000
kg
59.00
61950.00
Sub-Total(A1)
61950.00
61950.00
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar unload, carrying
1.050
ton
150.00
157.50
Sub-Total(B4)
157.50
157.50
Total(1)
62107.50
Add over head on Total(1)
5.0 %
3105.38
Total(2)
65212.88
Add Profit on Total(2)
10.0 %
6521.29
Total(3)
71734.16
Add VAT on Unit Price
5.5 %
4408.24
Add Income Tax on Unit Price
5.0 %
4007.50
Unit Price
80149.90
Say
80150
per ton