BREAKDOWN OF UNIT PRICE
Item: (C01U4) Concrete-3500psi-18th Floor Roof
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-3500ps
100.000
cft
250.00
25000.00
Sub-Total(A1)
25000.00
8828.75
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 18th Floor
84.118
sft
380.00
31964.84
Sub-Total(B4)
31964.84
11288.38
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
1800.000
cft
0.75
1350.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
2450.00
865.22
Total(1)
20982.35
Add over head on Total(1)
5.0 %
1049.12
Total(2)
22031.47
Add Profit on Total(2)
10.0 %
2203.15
Total(3)
24234.62
Add VAT on Unit Price
5.5 %
1489.28
Add Income Tax on Unit Price
5.0 %
1353.89
Unit Price
27077.78
Say
27078
per Cum