BREAKDOWN OF UNIT PRICE
Item: (C01P1) Concrete-4500psi -13th Floor
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 13th Floor
68.900
sft
179.85
12391.67
Sub-Total(B4)
12391.67
4376.12
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
1300.000
cft
0.75
975.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
2075.00
732.79
Total(1)
14997.10
Add over head on Total(1)
5.0 %
749.86
Total(2)
15746.96
Add Profit on Total(2)
10.0 %
1574.70
Total(3)
17321.65
Add VAT on Unit Price
5.5 %
1064.46
Add Income Tax on Unit Price
5.0 %
967.69
Unit Price
19353.80
Say
19354
per cum