BREAKDOWN OF UNIT PRICE
Item: (C01K1) Concrete-4500psi-9th Floor
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 9th Floor
86.455
sft
158.05
13664.21
Sub-Total(B4)
13664.21
4825.52
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
900.000
cft
0.75
675.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1775.00
626.84
Total(1)
15340.56
Add over head on Total(1)
5.0 %
767.03
Total(2)
16107.59
Add Profit on Total(2)
10.0 %
1610.76
Total(3)
17718.34
Add VAT on Unit Price
5.5 %
1088.84
Add Income Tax on Unit Price
5.0 %
989.85
Unit Price
19797.03
Say
19797
per cum