Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (C01J2) Concrete-3500psi-8th Floor Roof
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-3500ps
100.000
cft
250.00
25000.00
Sub-Total(A1)
25000.00
8828.75
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 8th Floor
86.455
sft
152.60
13193.03
Sub-Total(B4)
13193.03
4659.12
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
900.000
cft
0.75
675.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1775.00
626.84
Total(1)
14114.71
Add over head on Total(1)
5.0 %
705.74
Total(2)
14820.45
Add Profit on Total(2)
10.0 %
1482.04
Total(3)
16302.49
Add VAT on Unit Price
5.5 %
1001.83
Add Income Tax on Unit Price
5.0 %
910.75
Unit Price
18215.07
Say
18215
per cum