BREAKDOWN OF UNIT PRICE
Item: (C01J1) Concrete-4500psi-8th Floor
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 8th Floor
86.455
sft
152.60
13193.03
Sub-Total(B4)
13193.03
4659.12
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
800.000
cft
0.75
600.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1700.00
600.36
Total(1)
15147.67
Add over head on Total(1)
5.0 %
757.38
Total(2)
15905.06
Add Profit on Total(2)
10.0 %
1590.51
Total(3)
17495.56
Add VAT on Unit Price
5.5 %
1075.15
Add Income Tax on Unit Price
5.0 %
977.41
Unit Price
19548.12
Say
19548
per cum