BREAKDOWN OF UNIT PRICE
Item: (C01H1) Concrete-4500psi-7th Floor
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 7th Floor
86.455
sft
147.15
12721.85
Sub-Total(B4)
12721.85
4492.72
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
700.000
cft
0.75
525.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1625.00
573.87
Total(1)
14954.79
Add over head on Total(1)
5.0 %
747.74
Total(2)
15702.53
Add Profit on Total(2)
10.0 %
1570.25
Total(3)
17272.78
Add VAT on Unit Price
5.5 %
1061.46
Add Income Tax on Unit Price
5.0 %
964.96
Unit Price
19299.20
Say
19299
per cum