BREAKDOWN OF UNIT PRICE
Item: (C01A4) RCC (1:1.5:3)-Superstructure
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
22.000
bag
375.00
8250.00
Sylhet Sand (FM=2.2)
43.000
cft
54.00
2322.00
Stone-chips-20mm
86.000
cft
195.00
16770.00
Sub-Total(A1)
27342.00
9655.83
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
300.00
105.95
Total(1)
9761.77
Add over head on Total(1)
5.0 %
488.09
Total(2)
10249.86
Add Profit on Total(2)
10.0 %
1024.99
Total(3)
11274.85
Add VAT on Unit Price
5.5 %
692.87
Add Income Tax on Unit Price
5.0 %
629.88
Unit Price
12597.59
Say
12598
per Cum