BREAKDOWN OF UNIT PRICE
Item: (C01A3) Concrete 32 Mpa-Superstructure
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump above G.F.
100.000
cft
0.75
75.00
Vibrator
100.000
cft
5.00
500.00
Sub-Total(E1)
575.00
203.06
Total(1)
10091.26
Add over head on Total(1)
5.0 %
504.56
Total(2)
10595.82
Add Profit on Total(2)
10.0 %
1059.58
Total(3)
11655.41
Add VAT on Unit Price
5.5 %
716.25
Add Income Tax on Unit Price
5.0 %
651.14
Unit Price
13022.80
Say
13023
per Cum