BREAKDOWN OF UNIT PRICE
Item: (B13E) Suvey Work with Total station
Basis:1 no.
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Surveyor
0.033
mont
35000.00
1155.00
Survey Helper
0.033
nont
15000.00
495.00
Sub-Total(D1)
1650.00
1650.00
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Total Station-Rent
0.033
moth
75000.00
2475.00
Sub-Total(E1)
2475.00
2475.00
Total(1)
4125.00
Add over head on Total(1)
5.0 %
206.25
Total(2)
4331.25
Add Profit on Total(2)
10.0 %
433.13
Total(3)
4764.38
Add VAT on Unit Price
5.5 %
292.78
Add Income Tax on Unit Price
5.0 %
266.17
Unit Price
5323.32
Say
5323
per Day