BREAKDOWN OF UNIT PRICE
Item: (B13C3) Dewatering Substructure
Basis:1 no.
B0.Sub-Contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dewatering-Substructure
1.000
day
6865.00
6865.00
Sub-Total(B0)
6865.00
6865.00
Total(1)
6865.00
Add over head on Total(1)
5.0 %
343.25
Total(2)
7208.25
Add Profit on Total(2)
10.0 %
720.83
Total(3)
7929.08
Add VAT on Unit Price
5.5 %
487.26
Add Income Tax on Unit Price
5.0 %
442.97
Unit Price
8859.30
Say
8859
per Day