BREAKDOWN OF UNIT PRICE
Item: (B12C) Salvage-Joist Cutting, Pile Break
Basis:1 no.
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Salvage-Joist/ Pipe Cut
443.276
ton
10000.00
4432760.00
KIngPost Pile Breaking
9999.999
cft
250.00
2499999.75
Sub-Total(B3)
6932759.75
6932759.75
Total(1)
6932759.75
Add over head on Total(1)
5.0 %
346637.99
Total(2)
7279397.74
Add Profit on Total(2)
10.0 %
727939.77
Total(3)
8007337.51
Add VAT on Unit Price
5.5 %
492071.02
Add Income Tax on Unit Price
5.0 %
447337.29
Unit Price
8946745.82
Say
8946746
per LS