BREAKDOWN OF UNIT PRICE
Item: (B11D) Steel Shutter-Slab-Substructure
Basis:350 sft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shuttering-Sub-structure
350.000
sft
45.00
15750.00
Sub-Total(B3)
15750.00
484.38
D3.Shuttering-Hardware
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Shutter-use 3 time
350.000
sft
216.67
75834.50
MS Prop-use 20 times
145.000
no.
90.00
13050.00
Shutter Oil
350.000
sft
5.00
1750.00
Scaffolding-use 40 times
10.000
set
15.00
150.00
Nut-bolt, J-hook-use 8tim
12.000
kg
12.50
150.00
Hessain for Water Tight
350.000
sft
1.00
350.00
MS Box-50x100-use10 times
565.000
rft
13.50
7627.50
MS Pipe-50mm-use 20 times
180.000
rft
5.00
900.00
Sub-Total(D3)
99812.00
3069.65
Total(1)
3554.03
Add over head on Total(1)
5.0 %
177.70
Total(2)
3731.73
Add Profit on Total(2)
10.0 %
373.17
Total(3)
4104.90
Add VAT on Unit Price
5.5 %
252.26
Add Income Tax on Unit Price
5.0 %
229.32
Unit Price
4586.48
Say
4586
per Sqm