BREAKDOWN OF UNIT PRICE
Item: (B11C0) Steel Shutter-Footing
Basis:12 sft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shuttering-Sub-structure
12.000
sft
45.00
540.00
Sub-Total(B3)
540.00
484.38
D3.Shuttering-Hardware
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Wire Brush
0.100
no.
40.00
4.00
Shutter Oil
12.000
sft
5.00
60.00
MS Pipe-37mm-use 20 time
10.000
rft
4.25
42.50
Nut-bolt, J-hook-use 8tim
1.000
kg
12.50
12.50
Hessain for Water Tight
12.000
sft
1.00
12.00
Sub-Total(D3)
131.00
117.51
Total(1)
601.89
Add over head on Total(1)
5.0 %
30.09
Total(2)
631.98
Add Profit on Total(2)
10.0 %
63.20
Total(3)
695.18
Add VAT on Unit Price
5.5 %
42.72
Add Income Tax on Unit Price
5.0 %
38.84
Unit Price
776.74
Say
777
per Sqm