Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (B06B1) Concrete-C-35 in Basement-3
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-C-25
100.000
cft
250.00
25000.00
Sub-Total(A1)
25000.00
8828.75
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concret-Col/Bea
100.000
cft
50.00
5000.00
Sub-Total(B3)
5000.00
1765.75
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Sub-Total(E1)
800.00
282.52
Total(1)
10877.02
Add over head on Total(1)
5.0 %
543.85
Total(2)
11420.87
Add Profit on Total(2)
10.0 %
1142.09
Total(3)
12562.96
Add VAT on Unit Price
5.5 %
772.03
Add Income Tax on Unit Price
5.0 %
701.84
Unit Price
14036.82
Say
14037
per M3