BREAKDOWN OF UNIT PRICE |
Item: (B06A5) Concrete-32Mpa-Slab-Substructure |
Basis:100
cft |
|
A1.Material Cost-Civil |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
Ready Mix Concrete-4500ps |
100.000 |
cft |
280.00 |
|
|
|
|
Sub-Total(A1) |
28000.00
|
9888.20
|
|
B3.Labour-Substructur-2 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
Readymix Conc-Basemn-Slab |
100.000 |
cft |
38.50 |
|
|
|
|
Sub-Total(B3) |
3850.00
|
1359.63
|
|
D3.Shuttering-Hardware |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
Scaffolding-use 40 times |
5.000 |
set |
15.00 |
|
|
|
|
Sub-Total(D3) |
75.00
|
26.49
|
|
E1.Equipment Cost |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
Concrete Pump upto Gr.flr |
100.000 |
cft |
8.00 |
|
|
|
Vibrator |
100.000 |
cft |
5.00 |
|
|
|
|
Sub-Total(E1) |
1300.00
|
459.10
|
|
|
|
|
Total(1) |
|
11733.41
|
|
|
Add over head on Total(1)
|
5.0 % |
586.67
|
|
|
|
|
Total(2) |
|
12320.08
|
|
|
Add Profit on Total(2)
|
10.0
% |
1232.01
|
|
|
|
|
Total(3) |
|
13552.09
|
|
|
Add VAT on Unit Price
|
5.5 % |
832.81
|
|
Add Income Tax on Unit Price
|
5.0 % |
757.10
|
|
|
|
|
Unit Price |
|
15142.00
|
|
|
|
|
|
Say |
15142 |
per Cum |