Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (B05F1) Bitumins Water Proof Membran-Foun
Basis:1 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Water Proofing Membrane
1.100
sft
100.00
110.00
Sub-Total(A1)
110.00
1184.04
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bituminous Paper fixing
1.000
sft
10.20
10.20
Sub-Total(B3)
10.20
109.79
Total(1)
1293.83
Add over head on Total(1)
5.0 %
64.69
Total(2)
1358.52
Add Profit on Total(2)
10.0 %
135.85
Total(3)
1494.38
Add VAT on Unit Price
5.5 %
91.83
Add Income Tax on Unit Price
5.0 %
83.48
Unit Price
1669.69
Say
1670
per Sqm