Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (B05D1) One Layer Brick Flat Soling
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
300.000
no.
12.00
3600.00
Viti Sand (FM=0.5-0.8)
5.000
cft
15.00
75.00
Sub-Total(A1)
3675.00
395.58
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour/ Helper
1.000
no.
550.00
550.00
Mason1
0.250
no.
700.00
175.00
Sub-Total(B2)
725.00
78.04
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
0.091
no.
700.00
63.70
Sub-Total(D1)
63.70
6.86
Total(1)
480.47
Add over head on Total(1)
5.0 %
24.02
Total(2)
504.50
Add Profit on Total(2)
10.0 %
50.45
Total(3)
554.95
Add VAT on Unit Price
5.5 %
34.10
Add Income Tax on Unit Price
5.0 %
31.00
Unit Price
620.05
Say
620
per Sqm