BREAKDOWN OF UNIT PRICE
Item: (B05B3) Lean Concrete
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-2500ps
100.000
cft
200.00
20000.00
Sub-Total(A1)
20000.00
7063.00
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Readymix Concret-Substr
100.000
cft
35.00
3500.00
Sub-Total(B3)
3500.00
1236.03
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Sub-Total(E1)
800.00
282.52
Total(1)
8581.55
Add over head on Total(1)
5.0 %
429.08
Total(2)
9010.62
Add Profit on Total(2)
10.0 %
901.06
Total(3)
9911.68
Add VAT on Unit Price
5.5 %
609.10
Add Income Tax on Unit Price
5.0 %
553.73
Unit Price
11074.51
Say
11075
per Cum