BREAKDOWN OF UNIT PRICE
Item: (B04B) Bracing-MS Joist
Basis:1000 kg.
A2.Bracing Steel
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Joist
1000.000
kg
100.00
100000.00
MS Joist-Re-sale
800.000
kg
-20.00
-16000.00
Sub-Total(A2)
84000.00
84000.00
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bracing Installing -Joist
1000.000
kg
25.00
25000.00
Bracing Dismantling-Joist
1000.000
kg
20.00
20000.00
Sub-Total(B3)
45000.00
45000.00
Total(1)
129000.00
Add over head on Total(1)
5.0 %
6450.00
Total(2)
135450.00
Add Profit on Total(2)
10.0 %
13545.00
Total(3)
148995.00
Add VAT on Unit Price
5.5 %
9156.12
Add Income Tax on Unit Price
5.0 %
8323.74
Unit Price
166474.86
Say
166475
per TON