BREAKDOWN OF UNIT PRICE
Item: (B03D) Earth Excavation beyond 10m
Basis:100 cft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation from 31-36ft
100.000
cft
16.00
1600.00
Sub-Total(B3)
1600.00
565.04
Total(1)
565.04
Add over head on Total(1)
5.0 %
28.25
Total(2)
593.29
Add Profit on Total(2)
10.0 %
59.33
Total(3)
652.62
Add VAT on Unit Price
5.5 %
40.11
Add Income Tax on Unit Price
5.0 %
36.46
Unit Price
729.19
Say
729
per M3