BREAKDOWN OF UNIT PRICE
Item: (B03C) Earth Excavation from 10m to 15m
Basis:100 cft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation from 33-50ft
100.000
cft
25.00
2500.00
Sub-Total(B3)
2500.00
882.88
Total(1)
882.88
Add over head on Total(1)
5.0 %
44.14
Total(2)
927.02
Add Profit on Total(2)
10.0 %
92.70
Total(3)
1019.72
Add VAT on Unit Price
5.5 %
62.66
Add Income Tax on Unit Price
5.0 %
56.97
Unit Price
1139.35
Say
1139
per M3