BREAKDOWN OF UNIT PRICE
Item: (B03A0) Earthwork in Excavation-Layout
Basis:2000 sft
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.000
no.
500.00
1000.00
Foreman Supervisor
1.000
no.
1500.00
1500.00
Skilled Labour/ Helper
1.000
no.
550.00
550.00
Sub-Total(B2)
3050.00
16.42
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
1.250
no.
700.00
875.00
Sub-Total(D1)
875.00
4.71
Total(1)
21.12
Add over head on Total(1)
5.0 %
1.06
Total(2)
22.18
Add Profit on Total(2)
10.0 %
2.22
Total(3)
24.40
Add VAT on Unit Price
5.5 %
1.50
Add Income Tax on Unit Price
5.0 %
1.36
Unit Price
27.26
Say
27
per Sqm