BREAKDOWN OF UNIT PRICE
Item: (B03A) Earth Excavation upto 5m depth
Basis:100 cft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation upto 16ft dept
100.000
cft
15.00
1500.00
Sub-Total(B3)
1500.00
529.73
Total(1)
529.73
Add over head on Total(1)
5.0 %
26.49
Total(2)
556.21
Add Profit on Total(2)
10.0 %
55.62
Total(3)
611.83
Add VAT on Unit Price
5.5 %
37.60
Add Income Tax on Unit Price
5.0 %
34.18
Unit Price
683.61
Say
684
per m3