BREAKDOWN OF UNIT PRICE
Item: (B02C2) Pile Head Manual Finishing
Basis:1 cft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Head Finishing Manua
1.000
no,
3000.00
3000.00
Sub-Total(B3)
3000.00
105945.00
Total(1)
105945.00
Add over head on Total(1)
5.0 %
5297.25
Total(2)
111242.25
Add Profit on Total(2)
10.0 %
11124.23
Total(3)
122366.48
Add VAT on Unit Price
5.5 %
7519.73
Add Income Tax on Unit Price
5.0 %
6836.12
Unit Price
136722.32
Say
136722
per Each