Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (B02B8) Earth Filling with Earth Availabl
Basis:1000 cft
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
8.000
no.
500.00
4000.00
Skilled Labour/ Helper
2.000
no.
550.00
1100.00
Sub-Total(B2)
5100.00
180.11
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
0.500
no.
700.00
350.00
Sub-Total(D1)
350.00
12.36
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Compactor
100.000
cft
5.00
500.00
Sub-Total(E1)
500.00
17.66
Total(1)
210.12
Add over head on Total(1)
5.0 %
10.51
Total(2)
220.63
Add Profit on Total(2)
10.0 %
22.06
Total(3)
242.69
Add VAT on Unit Price
5.5 %
14.91
Add Income Tax on Unit Price
5.0 %
13.56
Unit Price
271.17
Say
271
per Cum