BREAKDOWN OF UNIT PRICE
Item: (B02B6) Cement Concreting
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
3.000
bag
375.00
1125.00
Local Sand (FM=1.2)
11.250
cft
18.00
202.50
Brick Chips-20mm
25.000
cft
110.00
2750.00
Sub-Total(A1)
4077.50
438.90
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC Work
25.000
cft
30.00
750.00
Sub-Total(B2)
750.00
80.73
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer Machine
25.000
cft
5.00
125.00
Sub-Total(E1)
125.00
13.46
Total(1)
533.09
Add over head on Total(1)
5.0 %
26.65
Total(2)
559.74
Add Profit on Total(2)
10.0 %
55.97
Total(3)
615.72
Add VAT on Unit Price
5.5 %
37.84
Add Income Tax on Unit Price
5.0 %
34.40
Unit Price
687.95
Say
688
per Sqm