BREAKDOWN OF UNIT PRICE
Item: (B02B4) Sand Filling
Basis:1000 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Viti Sand (FM=0.5-0.8)
1300.000
cft
15.00
19500.00
Sub-Total(A1)
19500.00
688.64
B1.Labour-Prelimnaries
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helmet
1.000
nos.
290.00
290.00
Safety Vest
1.000
nos.
200.00
200.00
Rubber Shoe
1.000
nos.
100.00
100.00
Sub-Total(B1)
590.00
20.84
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel-1
1.610
litr
65.00
104.65
Exacavator Rent
0.020
mont
99999.99
2000.00
Excavator Operator Foodin
0.020
day
3500.00
70.00
Sub-Total(E1)
2174.65
76.80
Total(1)
786.28
Add over head on Total(1)
5.0 %
39.31
Total(2)
825.59
Add Profit on Total(2)
10.0 %
82.56
Total(3)
908.15
Add VAT on Unit Price
5.5 %
55.81
Add Income Tax on Unit Price
5.0 %
50.73
Unit Price
1014.69
Say
1015
per Cum