BREAKDOWN OF UNIT PRICE
Item: (B02B2) Earth Back Filling
Basis:100 cft
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Filling
100.000
cft
15.00
1500.00
Sub-Total(B2)
1500.00
529.73
Total(1)
529.73
Add over head on Total(1)
5.0 %
26.49
Total(2)
556.21
Add Profit on Total(2)
10.0 %
55.62
Total(3)
611.83
Add VAT on Unit Price
5.5 %
37.60
Add Income Tax on Unit Price
5.0 %
34.18
Unit Price
683.61
Say
684
per Cum