BREAKDOWN OF UNIT PRICE
Item: (B01C3) Re-bar 60 Grade-Service Pile
Basis:1000 kg.
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Deforme Bar Grade-400(60)
1075.000
kg
59.00
63425.00
Sub-Total(A1)
63425.00
63425.00
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Fabriaction-Piling
1000.000
kg
15.00
15000.00
Sub-Total(B2)
15000.00
15000.00
Total(1)
78425.00
Add over head on Total(1)
5.0 %
3921.25
Total(2)
82346.25
Add Profit on Total(2)
10.0 %
8234.63
Total(3)
90580.88
Add VAT on Unit Price
5.5 %
5566.42
Add Income Tax on Unit Price
5.0 %
5060.38
Unit Price
101207.68
Say
101208
per Ton